T-Con Board - Post-Installation Checklist

After replacing the T-Con board, follow this checklist to ensure optimal performance and prevent repeat issues:

  1. Firmware Update – Check for the latest TV firmware and install if needed for panel compatibility.

  2. Panel ID Verification – In the service menu, confirm the panel ID matches the new board (only if applicable).

  3. Cable Connections – Ensure LVDS/ribbon cables are fully seated, locked, and clean.

  4. Voltage Test – Measure VGH, VGL, and VCOM voltages to confirm panel power stability.

  5. Factory Reset – Perform a reset to clear old error codes and recalibrate display settings.

  6. Visual Test – Play high-resolution video content to confirm clarity, colors, and no flickering.